Home > Cases > Coedbach Action Team Ltd v Secretary of State for Energy and Climate Change [2011] 1 Costs L.R. 70 & [2010] EWCA Civ 1494

John Litton QC acted for Helius Energy (the holder of a s.36 consent for the construction/operation of a biomass power station) in judicial review proceedings. Issues related to the application of the environmental impact assessment regulations. A further significant issue was whether the claimants should be entitled to a protective costs order following the decision in Garner.